Milestone | From Appointment Date | Contractual Dates as per CA | Target/Ach. Dates | Milestone Event |
MS-1 | 180 days | 26-11-2022 | 20-01-2023 | 20% of the Physical & Financial Progress. |
MS-2 | 365 days | 30-05-2023 | 30-05-2023 | 35% of the Physical & Financial Progress. |
MS-3 | 550 days | 01-12-2023 | 31-01-2024 | 75% of the Physical & Financial Progress. |
Schedule Completion Days | 730 days | 29-05-2024 | 30-06-2024 | shall have completed the Project in accordance with this Agreement. |
Payment Milestone |
Physical Progress |
Percentage of Project Cost |
Target/ Achieve Date |
I (First) |
05% |
4% |
13-07-22 |
II (Second) |
10% |
4% |
20-11-22 |
III (Third) |
20% |
4% |
28-01-23 |
IV (Fourth) |
30% |
4% |
25-03-23 |
V (Fifth) |
40% |
4% |
25-08-23 |
VI (sixth) |
50% |
4% |
Sep-23 |
VII (Seventh) |
60% |
4% |
Nov-23 |
VIII (Eighth) |
70% |
4% |
Dec-23 |
IX (Ninth) |
80% |
4% |
Feb-24 |
X (Tenth) |
90% |
4% |
Apr-24 |
40% (forty per cent) of the Bid Project Cost , adjusted for the Price Index Multiple, shall be due and payable to the Concessionaire in 10 (Ten) equal instalments of 4% (four per cent) each during the Construction Period.
60% of the bid cost shall be paid in 15 years biannually Annuity.
Items Description (MCW) |
Unit |
Scope (3-Lane) |
Actual Ach. upto Mar-24 |
Balance (3-Lane) |
Embankment Top |
Km |
75.51 |
57.14 |
18.37 |
Sub-Grade |
Km |
75.51 |
53.00 |
22.51 |
GSB |
Km |
75.51 |
49.94 |
25.57 |
CTB |
Km |
75.51 |
47.42 |
28.09 |
AIL |
Km |
75.51 |
45.44 |
30.07 |
DBM |
Km |
75.51 |
43.79 |
31.72 |
BC |
Km |
75.51 |
2.26 |
73.25 |
Items Description (MCW) |
Unit |
Scope As Per CA |
Actual Ach. upto Mar-24 |
WIP |
Box Culvert (In situ) |
Nos |
45 |
34.5 |
3 |
Box Culvert (Precast) |
Nos |
27 |
22 |
|
Pipe Culvert |
Nos |
43 |
|
|
LVUP |
Nos |
7 |
7 |
|
VUP |
Nos |
3 |
2 |
1 |
VOP |
Nos |
3 |
|
3 |
Minor Bridge |
Nos |
13 |
4.5 |
6.5 |
Major Bridge |
Nos |
4 |
|
11 |
Viaduct |
Nos |
13 |
|
13 |
ROB |
Nos |
- |
|
|
Interchange VUP |
Nos |
3 |
2 |
1 |
Total |
Nos |
161 |
75 |
38.5 |
S No. |
Structur e Type |
Structure Ch. |
Span Configurat ion |
Heads |
Open Fdn |
Pile |
Pile Cap |
Pier |
Pier Cap |
Post Tensione d Girder |
Pre Tensione d Girder |
Girder Launchin g |
Slab |
Target Date of Completion |
1 |
MJB |
262+018 |
4 X 30 |
Scope |
|
56 |
10 |
10 |
10 |
32 |
|
32 |
8 |
31-05-2024 |
Ach. |
|
56 |
10 |
10 |
10 |
32 |
|
32 |
|
|||||
2 |
MJB |
264+396 |
2 X 31 |
Scope |
|
48 |
6 |
6 |
6 |
16 |
|
16 |
4 |
31-05-2024 |
Ach. |
|
45 |
6 |
6 |
6 |
16 |
|
16 |
|
|||||
3 |
Viaduct |
268+365 |
39/41 X 35.7 |
Scope |
56 |
156 |
26 |
82 |
82 |
|
320 |
320 |
80 |
31-08-2024 |
Ach. |
56 |
156 |
26 |
37 |
37 |
|
204 |
|
|
|||||
4 |
Viaduct |
270+045 |
9 X 35.70 |
Scope |
20 |
|
|
20 |
20 |
|
72 |
72 |
18 |
31-10-2024 |
Ach. |
17 |
|
|
|
|
|
12 |
|
|
|||||
5 |
Viaduct |
270+475 |
9/3 X 35.7 |
Scope |
13 |
|
|
13 |
13 |
|
48 |
48 |
12 |
31-10-2024 |
Ach. |
10 |
|
|
|
|
|
|
|
|
|||||
6 |
Viaduct |
270+965 |
14 X 35.7 |
Scope |
30 |
|
|
30 |
30 |
|
112 |
112 |
28 |
31-12-2024 |
Ach. |
29 |
|
|
|
|
|
|
|
|
|||||
7 |
Viaduct |
271+630 |
11 X 35.7 |
Scope |
24 |
|
|
24 |
24 |
|
88 |
88 |
22 |
31-12-2024 |
Ach. |
5 |
|
|
|
|
|
|
|
|
|||||
8 |
Viaduct |
273+500 |
15/16 X 35.7 |
Scope |
33 |
|
|
33 |
33 |
|
124 |
124 |
31 |
31-08-2024 |
Ach. |
25 |
|
|
|
|
|
52 |
|
|
S No. |
Structure Type |
Structure Ch. |
Span Configura tion |
Heads |
Open Fdn |
Pile |
Pile Cap |
Pier |
Pier Cap |
Post Tensione d Girder |
Pre Tensione d Girder |
Girder Launching |
Slab |
Target Date of Completion |
09 |
Viaduct |
279+445 |
35 x 35.7 |
Scope |
42 |
204 |
34 |
76 |
76 |
|
296 |
296 |
74 |
31-10-2024 |
Ach. |
42 |
82 |
34 |
1 |
1 |
|
272 |
|
|
|||||
10 |
Viaduct |
280+650 |
5 x 35.7 |
Scope |
12 |
|
|
12 |
12 |
|
40 |
40 |
10 |
31-07-2024 |
Ach. |
12 |
|
|
2 |
2 |
|
|
|
|
|||||
11 |
Viaduct |
281+690 |
3 x 40 |
Scope |
8 |
|
|
8 |
8 |
24 |
|
24 |
6 |
31-07-2024 |
Ach. |
8 |
|
|
|
|
|
|
|
|
|||||
12 |
MJB |
283+440 |
3 X 40 |
Scope |
|
48 |
8 |
8 |
8 |
24 |
|
24 |
6 |
31-07-2024 |
Ach. |
|
48 |
8 |
3 |
|
24 |
|
|
|
|||||
13 |
Viaduct |
286+590 |
3 x 40 |
Scope |
8 |
|
|
8 |
8 |
24 |
|
24 |
6 |
15-06-2024 |
Ach. |
8 |
|
|
8 |
8 |
24 |
|
|
|
|||||
14 |
Viaduct |
287+890 |
2 x 30 |
Scope |
6 |
|
|
6 |
6 |
16 |
|
16 |
4 |
31-05-2024 |
Ach. |
6 |
|
|
6 |
6 |
16 |
|
|
|
|||||
15 |
Viaduct |
288+200 |
3 x 40 |
Scope |
8 |
|
|
8 |
8 |
24 |
|
24 |
6 |
31-05-2024 |
Ach. |
8 |
|
|
8 |
8 |
24 |
|
|
|
|||||
16 |
Viaduct |
288+750 |
2 x 30 |
Scope |
6 |
|
|
6 |
6 |
20 |
|
20 |
4 |
15-05-2024 |
Ach. |
6 |
|
|
6 |
6 |
20 |
|
20 |
|
|||||
17 |
MJB |
291+790 |
3 X 30 |
Scope |
|
48 |
8 |
8 |
8 |
24 |
|
24 |
6 |
31-05-2024 |
Ach. |
|
48 |
8 |
8 |
8 |
24 |
|
12 |
|